For the complete documentation index, see llms.txt. This page is also available as Markdown.

Server room

A server room is represented in GLPI by a schematic map. This map gives the space available in the room to place racks.

A server room can be attached to a data center and to a location.

A GLPI server room

You can specify the details of your data center:

  • Name

  • Data center position

  • Data center

  • Location

  • Number of columns

  • Number of rows

  • Cell width

  • Cell height

  • Background image (blueprint)


Racks

This tab allow to display and modify the map of a server room by adding directly on the map the racks composing the room.

If the room contains many elements, it is possible to switch from a grid view to a list view.

Map of a server room

The map is a grid defined by a number of lines and columns. One rack consumes one square.

The background image can enhance room visualization, in particular if this image has been generated by a dedicated tool.

Impact Analysis

Impact analysis enables an infrastructure diagram to be drawn up, showing the dependencies and impacts in the event of equipment loss. This can be saved and exported.

Go to Impact Analysis


Management

Management of financial and administrative information, this information is visible in the 'Management' tab on the computer's form.

Go to Financial & administrative information


Contracts

GLPI supports contracts management, in order to manage contract types such as loan, maintenance, support...

Contracts management allows to:

  • make an inventory of all contracts related to the organization assets

  • integrate contracts in GLPI financial management

  • anticipate and follow contract renewal.

  • Documents

The document tab lets you link different types of file to a material (PDF, txt, png, etc.) You can attach a document already uploaded to GLPI or add a new one directly from this tab.

Go to Contacts


Documents

The document tab lets you link different types of file to a material (PDF, txt, png, etc.) You can attach a document already uploaded to GLPI or add a new one directly from this tab.

Go to Documents


Links offer several possibilities. Send the GLPI object file to another URL of your choice, or generate an RDP file, for example.

Go to Links


Tickets

View all tickets linked to the item.

Go to Tickets


Problems

This tab refers to all hardware-related problems. Problems can also be linked to tickets, projects, etc. This allows you to have a complete scenario when necessary.

Go to Problems


Changes

Changes lists all changes related to a material. From this tab, you can't link a change directly, you can do it from Assistance > Changes > Items. You can create a new change from this page, which will be linked to the material you have selected.

Go to Changes


History

The History tab is used to show any changes made to an item. The following information about the changes is available:

  • ID of the change.

  • Date and time the change was made.

  • User who made the change. If this field is not filled, it means that the action was done automatically (For example: automatic inventory update).

  • Field that was changed.

  • Description of the change that was made.

The description of the change represents either the difference between the old and the new value (For example with location field: Change HQ to Remote Office A), or the explanation of the action which was carried out (For example: Uninstallation of a software: "Gimp 2.0").

For dropdowns or objects with a parent/child relationship, the modification of a child will appear in the history of the parent element.


All Information

For an item, all information is displayed on one page from the All tab. This shows all of the tabs of an object's form in one view, one below the other.